Construction Technology II - 7.01
Quiz
A short framing member that fills the space between the rough sill and the soleplate is a:
- Cripple stud.
- Spacer.
- Top plate.
- Trimmer stud.
The framing member that forms the side of a rough opening for a window or door is the:
- Common stud.
- Header.
- Sole plate.
- Trimmer stud.
The framing member that distributes the weight of the structure over a door or window opening is the:
- Cripple stud.
- Header.
- Top plate.
- Trimmer stud.
Pieces of 2 × 4 placed horizontally between each pair of studs are used to:
- Brace the frame.
- Hold strong-backs.
- Provide a place for carpenters to stand when installing ceiling joists.
- Retard the spread of fire.
The supporting member above door or window openings are:
- Braces.
- Headers.
- Plates.
- Trimmers.
The top and bottom horizontal members of a wall frame are called:
- Headers.
- Plates.
- Sills.
- Trimmers.
The bottom window framing member is called a:
- Ledger.
- Mud sill.
- Rough sill.
- Sole plate.
Shortened studs above and below rough openings are called:
- Cripples.
- Jacks.
- Shorts.
- Studs.
A wood block used as a filler piece and for support between framing members is called:
- Blocking.
- Headers.
- Plates.
- Studs.
The full-length stud next to the trimmer stud in a wall opening is a:
- Cripple stud.
- Jack.
- King stud.
- Rough sill.
A wall that sub-divides space within a building is a/an:
- Divider.
- Opening.
- Partition.
- Section.
The LOWEST horizontal member of a wall to which studs are nailed is a:
- Double plate.
- Rough sill.
- Sole plate.
- Top plate.
What is the MAIN vertical framing member in a wall?
- Cripple
- Jack
- Stud
- Trimmer
What is the upper framing member of a wall that is used to carry the roof trusses?
- King stud
- Partition
- Sole plate
- Top plate
The three types of engineered wood products that can be used for headers are LVLs, PSLs, and:
- Glulams.
- OSB.
- TGIs.
- Web-trusses.
What is used to distribute weight over a built-up header?
- Cripples
- Plates
- Sheathing
- Trimmers
Pieces of 2 x 4s installed in the level position between studs are used for:
- Bracing.
- Firestops.
- Shims.
- Support.